Home Projects

Boggabri Coal Mine 11kV Relocation

See all Projects

The Boggabri 11kV relocation project was an expansion project for the Boggabri Coal Mine. Completed under very strict mining rules this project was undertaken to expand the mine’s capacity of coal from 1.6Mtpa to 6.5Mtpa. This involved the upgrading, relocating, and building of new power lines.

This project included a new 132kV Transmission line expanded mine infrastructure and supply, construct, testing and commissioning of approximately 8km of 11kv overhead lines and associated underground lines.

Key Challenges:
  • Upgrading and constructing the transmission line
  • Underground lines

Related Projects

Tamworth to Gunnedah 66kV Transmission Line

The Tamworth to Gunnedah 66kv Transmission Line project for Country Energy included the refurbishment of existing infrastructure and a new transmission line at Tamworth, NSW....

View Project
Gullen Range Wind Farm 33kV Transmission Line

The scope of this project included the construction of a 33kv Transmission line which became the internal connection between the two halves of the Gullen...

View Project
Bega Bypass and Street Lighting

This project included the Bega Bypass HV Conflict Area Relocation and Street-lighting for Roads and Maritime and John Holland. The project included the design and...