Project Energy Connect (PEC)


3 x 330kV / 275kV

TRANSFORMERS


765

PIER FOOTINGS



21x

GANTRY STRUCTURES


161km

CONTROL CABLE



6x

CONTROL BUILDINGS


100+ OUTAGES

ZERO LOAD LOST


Overview
CPP Scope of Works

Deliverables

  • Consolidated Power Industries (CPI)
  • CPP Civil
  • Transmission Lines team
  • Asset Management Services

  • 75,000+ Design/Engineering hours
  • 270,000+ Construction hours
  • 42,000+ Commissioning hours
  • 6,000 +/- Drawings
  • 160,000m control cable
  • 200+ control panels built by CPI
  • 600 individual HV tests
  • 100+ outages, zero load lost

2023 – 2025
Design and construction of 330kV Substation, OHL 330kV Connection to Munmorah Substation and 850MW BESS.
Colongra, NSW
2020 – 2021
Large solar PV system with single-axis tracking and ground-mounted panels, generating 395 GWh annually.
Suntop, NSW
2020 – 2023
Australia’s largest solar farm, with a 460 MWp capacity and a 270 MW / 540 MWh battery.
Hopeland, Queensland