Location: Near Dapto, NSW
The scope of this project is to install OHEW, OPGW conductor and replace Insulators near Dapto, NSW.
The Works on this project Include TL10 and TL11 330kV Twin Conductor Insulator Replacement on 36 Strain Towers, TL11 OHEW Replacement from Str. 0 Dapto Substation to Sydney South Substation Str. 156, incl. Earth Peak upgrades and TL10 OHEW and OPGW from Str. 2 Dapto Substation to Str. 26 West of Dombarton Substation, incl. Earth Peak upgrades.
On this project, we have had to design new earth peak OHEW/ OPGW brackets with 2 attachment points for maintenance purposes.
We have also designed and engineered rated insulator lifting cradles with single point lift at 500kg SWL.
The Tamworth to Gunnedah 66kv Transmission Line project for Country Energy included the refurbishment of existing infrastructure and a new transmission line at Tamworth, NSW....
The scope of this project included the construction of a 33kv Transmission line which became the internal connection between the two halves of the Gullen...
This project included the Bega Bypass HV Conflict Area Relocation and Street-lighting for Roads and Maritime and John Holland. The project included the design and...