Home Projects

Tamworth to Gunnedah 66kV Transmission Line

See all Projects
Project Details

Location: Tamworth, NSW

The Tamworth to Gunnedah 66kv Transmission Line project for Country Energy included the refurbishment of existing infrastructure and a new transmission line at Tamworth, NSW.

Specific work scope included the installation of a twin circuit steel pole transmission line including optical ground wire (OPGW), and tie into the existing substation. At Gunnedah, twin transmission lines were refurbished, and new conductors and overhead earth wire (OHEW) were installed.

The conductors and OPGW were installed utilizing tension stringing techniques.

Key Challenges:
  • Optical ground wire (OPGW) installation
  • Transmission line refurbishment
  • Construction of a twin circuit steel pole
  • Overhead earth wire (OHEW) installed

Related Projects

Gullen Range Wind Farm 33kV Transmission Line

The scope of this project included the construction of a 33kv Transmission line which became the internal connection between the two halves of the Gullen...

View Project
Bega Bypass and Street Lighting

This project included the Bega Bypass HV Conflict Area Relocation and Street-lighting for Roads and Maritime and John Holland. The project included the design and...

View Project
TransGrid Bathhurst OPGW

We successfully installed OPGW on over 300 towers near Bathurst, NSW for Transgrid. This involved stringing OPGW on TL72 330kV/132kV Tower Line of 67 Structures,...

View Project