Our team successfully completed the Moree Bypass HV Conflict Area Relocations and street-Lighting for Roads and Maritime and Hazel Bros. This involved the design and installation of high voltage overhead and underground infrastructure and street-lighting for the Moree Bypass.
Work on the distribution network was carried out under outage arrangements with our authorized linesperson as the access recipients. The works required extensive traffic management and working harmoniously with other subcontractors in a confined work site.
The project was delivered without quality non-conformances, environmental incidents or lost time injuries.
Key Challenges:
The Tamworth to Gunnedah 66kv Transmission Line project for Country Energy included the refurbishment of existing infrastructure and a new transmission line at Tamworth, NSW....
The scope of this project included the construction of a 33kv Transmission line which became the internal connection between the two halves of the Gullen...
This project included the Bega Bypass HV Conflict Area Relocation and Street-lighting for Roads and Maritime and John Holland. The project included the design and...
We are committed to successfully and safely delivering solutions to meet the needs of our clients.
Learn MoreSend us a message to get in touch with us for any comments, concerns, or questions you may have.
Learn More